Mountain View O.P Gym

Full execution and finishing

Completed gym building with Mountain View signage and a planted entrance walkway
Completed
Completed gym building with Mountain View signage and a planted entrance walkway

Full execution and finishing of a gym building in 6th of October, from the steel structure through to the completed exterior.

FORMED carried out the full execution and finishing of the O.P Gym at Mountain View in 6th of October.

The project record follows the building from a 3D massing model, through the erection of the steel frame and roof structure, to the enclosure, cladding and finished entrance.

Scope of work
  1. 01Full execution
  2. 02Finishing
  3. 03Fit-out
Location
6th of October
Sector
Commercial
Services
Fit-Out, Finishing Works
In the images
1 design visual, 9 site photographs and 1 photograph of the finished work.

Design and build

On site, and the finished result.

Both are photographs of this project.

Steel frame being erected on site, with structural members laid out on the ground
On site — photographSteel frame being erected on site, with structural members laid out on the ground
Completed gym building with Mountain View signage and a planted entrance walkway
Completed — photographCompleted gym building with Mountain View signage and a planted entrance walkway

Chapter 01

Design visuals

3D visuals produced during the design stage, showing the intended result. These are not photographs.

1 image

3D massing model of the gym building and roof

Chapter 02

On site

Photographs taken on site while the work was under way.

9 images

  1. 02.01Steel frame being erected on site, with structural members laid out on the ground
  2. 02.02Steel portal frame rising beside the adjacent sports pitch
  3. 02.03Roof steelwork seen from below during construction
  4. 02.04Gym hall under its steel roof structure during construction
  5. 02.05Wide view of the roof structure and open gym floor during construction
  6. 02.06Steel roof structure spanning the gym floor
  7. 02.07Perimeter walls rising inside the steel structure
  8. 02.08External cladding and roof edge being completed, with safety netting in place
  9. 02.09Roof cladding and parapet along the building edge

Next project

Mountain View Lake

Landscape · 6th of October